Nortons hiab with the boom extended out over a city-centre pavement
Operated · Mainland UK

Long reach hiab hire

Across a site, over a fence line, into a yard the lorry cannot enter. The reach is only half the answer — here is what the crane will lift once it gets there.

Reach and weight

Reach and capacity trade against each other

Every loader crane lifts less the further out it goes. A supplier who answers "how far can it reach?" without asking "how heavy is it?" has not yet quoted your job.

Our furthest-reaching crane offers a maximum reach of 19.6 m. Close in it lifts over 8 tonnes. Right out at full reach it lifts a fraction of that. Same crane, same day, same driver / operator — the difference is caused entirely by distance.

All five load charts

Nortons hiab standing on its stabiliser legs with the boom raised and the main hook out over the yard
On the job

What long reach looks like in practice

Five frames from one job — paving slabs off a city-centre rooftop, where nothing could be craned conventionally: the load had to come down from a roof, over a live footway, onto a lorry parked in a bus lane. The sixth is a different site, worked from outside the barrier line.

Nortons hiab parked alongside a city-centre building for a rooftop lift

The standing position

The only place the lorry could stand was the carriageway alongside the building. Everything else about the lift followed from that one constraint.

Paving slabs lifted from a rooftop by a Nortons hiab

Off the roof

Slabs lifted from roof level in graded loads rather than one heavy pick, because capacity at that radius set the limit, not the total tonnage.

Nortons hiab with outrigger legs set down on a city footway

Legs down on the footway

At long radius most of the machine goes through the leg on that side, and that leg was standing on a public footway. Pads sized for the ground rather than for what was in the locker.

Load being lowered onto a Nortons hiab lorry in a city street

Down to the deck

Loads brought down under control and landed on the lorry that would take them away. No second crane, no transfer, no second visit.

Street-level view of a Nortons hiab working against a city building

What it looks like from the street

The reason long reach exists: from pavement level the whole operation is one lorry, four legs and a boom that goes where a crane could not be built.

Nortons hiab reaching in over a barrier line to place a large unit

In over the barrier line

A different site, the same problem. The wagon could get no closer than the barrier line, so the reach did the walking and nothing had to be moved to let it in.

The real constraint

It is rarely the crane. It is where the lorry can stand.

On almost every long reach enquiry, the limiting factor turns out to be the standing position rather than the boom. A crane that reaches nineteen metres is no use if the only place the lorry can stop is twenty-five metres from the drop.

The second constraint is the ground under the outriggers. At long radius, most of the machine's weight goes through one leg, so what the surface will take matters as much as what the boom will do.

Both are answerable before anyone travels. Tell us where the lorry would have to stop, how far it is from there to the drop point, and what the ground is made of, and we will tell you whether it works.

Outrigger pad sizes by ground type

Nortons hiab lifting a large plant unit off the flatbed alongside a hospital building
Two Nortons hiabs lifting a long panel together on lifting frames
When one crane is not the answer

Two cranes, one lift plan

Long panels, frames and glazing units are often not heavy, but they are unbalanced — and holding a six-metre panel level on one hook at long radius is how they get damaged.

A dual lift puts a crane on each end. It runs to one lift plan, with one appointed person and one banksman controlling both machines, and it usually places the load faster than a single crane working at the edge of its chart.

It is also the answer when the drop point can be approached from two sides but neither side alone gives enough radius.

How lifts are planned

A Nortons hiab lorry set up in a narrow residential street with a stabiliser leg down on a spreader pad against a brick wall
Where it stands

Reach starts with where the lorry can park

On a long reach job the standing position decides everything else. A street like this one gives you one place to put the vehicle, one width to put the legs out into, and one surface to put them down on.

Everything after that is arithmetic. From that standing position, how far out is the landing point, and what does the load weigh at that radius? Capacity falls steeply the further the boom goes, so a job that is straightforward at six metres can be impossible at fifteen.

You do not need to work any of that out. Tell us roughly where the lorry could stop and roughly where the thing has to end up, and a photograph from the road answers most of the rest.

The numbers

Reach, height and what it lifts out there

Hydraulic outreach is boom only. Lifting height is measured from the ground. Both come off the manufacturer data sheets.

Nortons loader cranes by outreach, lifting height and capacity at maximum radius
Crane Hydraulic outreach Lifting height Capacity at max radius
HIAB X-HiPro 858 E-8 19.6 m 22.1 m 2,900 kg at 19.4 m
HIAB 855 E-8 HiPro 19.4 m 2,900 kg at 19.4 m
HIAB 658 EP-6 HiPro 17 m 19.5 m 2,820 kg at 16.9 m
HIAB 622 E-6 HiPro 15.8 m 18.5 m 2,960 kg at 15.8 m
HIAB X-HiPro 558 EP-5 14.5 m 3,150 kg at 14.5 m
Common questions

Long reach hiab hire, answered

How far can a long reach hiab actually reach?

Our furthest-reaching crane, the 858 rigid, offers a maximum reach of 19.6 metres. What matters more than the headline is what it will lift out there, because reach and capacity trade against each other on every loader crane ever built. The 858 lifts over 8 tonnes and carries up to 5.5 tonnes, so the honest question is always "how much, how far?" rather than "how far?".

How far from the lorry can you place a load?

As far out as the chart allows for that weight, and that is the honest limit rather than the headline reach. In practice the limiting factor is not the crane at all, it is where the lorry can stand and get its stabiliser legs down. Tell us the standing position and the distance to the drop point and we can answer before anyone travels.

What do you need from me to check a long reach job?

The weight of the load, the distance from where the lorry can stand to where the load has to land, and what is in between — a fence line, a boundary wall, parked cars, overhead cables. Describe those in words and we can usually settle it there and then; where it is borderline we come and look before anyone commits.

Is a long reach hiab cheaper than a mobile crane?

For a delivery, usually, because the crane arrives with the load already on it and there is nothing separate to hire. Where a mobile crane wins is height above roughly twenty metres, very heavy loads at long radius, or a lift that has to stand on site for days. We will tell you which one your job is.

Can two hiabs lift one item together?

Yes, and for long panels or frames a dual lift is often better than one crane at maximum radius. It runs to a single lift plan with one appointed person and one banksman controlling both machines.

Do you need extra ground protection at long radius?

The further the load goes out, the more load goes through the outrigger on that side, so what the ground will take matters as much as what the boom will do. The minimum spreader pad sizes by ground type are published on the lifting capacity page. On mud, peat or marsh there is no permissible load at all — the pads do not fix that, and no reputable driver / operator will pretend otherwise.

Is long reach hiab hire available near me?

Anywhere in mainland Britain. The long reach vehicles live at the Manchester yard with the rest of the fleet, so the North West is usually same day or next morning and the rest of the country next day. Reach is the reason people ring rather than the distance, so tell us what is in the way and we will tell you whether it works.

Do I need to measure the distance before I ring?

No. A rough idea helps but a description works just as well - where the lorry can stand, what is between it and the landing point, and whether that is a wall, a fence, a hedge or a row of parked cars. We would rather work it out from a sentence and a photograph than have you climbing about with a tape measure.

The 858 — our longest reach  ·  Load charts  ·  Truck-mounted crane hire

Tell us where it has to land

A sentence about the load and where it has to end up is enough. Working out the reach is our job, not yours.

ALLMI trained driver / operators · RAMS, method statements and lift plans · Euro VI clean air zone compliant fleet, renewed by continual investment in new wagons · All our accreditations