What a lift plan is, and what it is not

Every site asks for RAMS. Fewer sites know what a good one contains, or why the useful part is the bit about the ground.

Published by Nortons Hiab Services Ltd

A Nortons Volvo rigid working inside a steel-framed warehouse with a crane extended
A planned lift inside a building

Ask for RAMS and you will get a document. Whether it is any use depends on whether anybody wrote it about your site or whether it is a template with your name typed into the header.

The two documents

A risk assessment lists what could go wrong and what is being done about it. A method statement describes, in order, what will actually happen on the day. They usually travel together, which is where RAMS comes from. On top of that a lift needs a lift plan, which is the specific engineering: this load, this crane, this radius, this ground.

What a real lift plan contains

  • The weight of the load and how that weight was established, not assumed
  • The crane, the configuration, and the capacity at the radius being used — with the margin stated
  • Where the vehicle stands, where the outriggers land, and the spread
  • The ground bearing pressure under each leg and what pads are needed to keep it inside what the ground will take
  • The lifting accessories, their rating, and how the load is attached
  • Exclusion zone, who controls it, and what happens to pedestrians and other trades
  • Wind limit and the abort criteria — the conditions under which the lift does not happen
  • Who is the appointed person, who is slinging, who is the banksman

The part that gets skipped

Ground bearing pressure. An outrigger concentrates a very large force into a very small area. Our 855 puts up to 220 kN through a single stabiliser. On soft cohesive ground that needs something in the order of five and a half square metres of pad to stay inside what the ground will bear; on compacted crushed stone it is well under a square metre. Same crane, same load, seven times the pad.

That is not a theoretical point. Basements, drainage runs, service ducts, fresh tarmac and recently backfilled trenches have all put lorries where nobody wanted them.

What we do

Site-specific RAMS and a lift plan for the actual job, turned round quickly, with the ground pressure worked for the ground you have told us about. Not a template. If you send us a site plan and tell us where the lorry will stand, that is usually enough to write it from.

Health, safety and RAMS · Load charts and ground pressure data · What we are accredited to

Next

More like this

Hiring Guides

One lorry twice, or two lorries once

Two units to move and one lorry available. Whether that is one lorry going twice or two lorries going once depends almost entirely on the distance.

Everything we have written

Tell us what needs lifting